Budget

Construction
$2,285,000
Science Labs: 3,000 s.f. @ $135/s.f.
Resource Center: 6,000 s.f. @ $130/s.f.
General Classroom & Administrative:
11,000 s.f. @ $100/s.f.

Site Development $350,000
Includes paved surface parking for 150 cars
Curbs, sidewalks and site preparation

Fixtures, Furnishings & Equipment $200,000
Construction costs

Project Development $360,000
Architect’s Fees
Legal/Permitting
Campaign Costs
$3,195,000
Contingency

$100,000
Financing $360,000
 
TOTAL FUNDRAISING NEEDS

$3,655,000
Land $1,000,000
 
PROJECT TOTAL $4,655,000
 